Environmental Utilities Operations Center project
The city approved a 150-acre operations center west of town — a new corporation yard plus a waste transfer facility that serves as a backup if the regional WPWMA facility fails state compliance. Placer County wanted a delay, but the council certified the EIR and moved ahead; actual construction is likely four to five years out.
Phillip Road Site Draft EIR adequacy
Residents say the environmental study for the 176-acre Phillip Road project describes a low-intensity village while the infrastructure plans point to a data center or freight hub. Concerns include a 49 MVA substation, 45 megawatts of diesel backup generators, 175 million gallons a year of recycled water for cooling, and a six-lane freight route on Blue Oaks Boulevard.