Council Member· 2022-12-21 to 2026-12-01
Pauline Roccucci
Roseville
No biography on file yet.
Voice
- Meetings spoken in
- 17
- Total speaking time
- 1:10:18
- Avg per meeting
- 4:08
- Segments
- 889
Want every word Roccucci has said?
The OpenCity MCP for Claude.ai answers questions like “what has Roccucci said about housing this year” with one prompt — full speaking history, with YouTube timestamps.
Top issues during term (4)(Environment)
Environmental Utilities Operations Center project
Major capital project; cost figures were not stated on the record, with activity expected in roughly four to five years.
Gas-powered leaf blower ban request
Extension of DEIR comment period
Phillip Road Site Draft EIR adequacy
Residents worry data center-scale utility demands could drive up water and electric rates for existing residents.
Decisions during term (21)
Recorded while Roccucci was in office — not necessarily decisions they moved, spoke to, or voted on.
Dry Creek Wastewater Treatment Plant Cogenerations Maintenance and Repair Services – Sole Source Annual Contract Purchase Agreement (ENVIRONMENTAL UTILITIES DEPARTMENT - TECHNICAL SERVICES)
Dry Creek Wastewater Treatment Plant Operations and Laboratory Building Project – Construction Change Order Authority Increase (ENVIRONMENTAL UTILITIES DEPARTMENT - TECHNICAL SERVICES)
North American Society of Trenchless Technology No-Dig North Conference – Out-of-Country Travel Approval (ENVIRONMENTAL UTILITIES DEPARTMENT - TECHNICAL SERVICES)
Second Reading - Environmental Utilities Nonfunctional Turf - Municipal Code Amendment (ENVIRONMENTAL UTILITIES DEPARTMENT - STRATEGIC AFFAIRS DIVISION )
Environmental Utilities Operations Center Project and Final EIR (Item 36)
Cirby Way Water Pipeline Repair Project (RFP #08-158) - Design-Assist Construction Agreement & Budget Adjustment (ENVIRONMENTAL UTILITIES DEPARTMENT - WATER)
Monitoring and Transmitting Equipment and Parts - Sole Source Purchase Order (ENVIRONMENTAL UTILITIES DEPARTMENT - WASTEWATER)
Ultraviolet Disinfection Equipment – Sole Source Annual Purchase Order (ENVIRONMENTAL UTILITIES DEPARTMENT - TECHNICAL SERVICES)
Dry Creek Wastewater Treatment Plant Foul Air Collection System and Biofilter Rehabilitation Project - Design-Assist Construction Contract and Budget Adjustment (ENVIRONMENTAL UTILITIES DEPARTMENT - TECHNICAL SERVICES)
Wastewater Collections Main Lining Materials - Purchase Order (ENVIRONMENTAL UTILITIES DEPARTMENT - WASTEWATER)
Sewer Lift Station 19 Force Main Condition Assessment - Professional Services Agreement (ENVIRONMENTAL UTILITIES DEPARTMENT - WASTEWATER)
Waste Services Cost-of-Services Rate Study – Professional Services Agreement (ENVIRONMENTAL UTILITIES DEPARTMENT)
Water Meters and Related Parts - Sole Source Purchase Order (ENVIRONMENTAL UTILITIES DEPARTMENT)
Wastewater Climber Screens Parts and Equipment – Sole Source Purchase Order (ENVIRONMENTAL UTILITIES DEPARTMENT - WASTEWATER)
RiverArc Project Related to the Third Pump at Pritchard Lake Diversion Facility - Cost Share Agreements (ENVIRONMENTAL UTILITIES DEPARTMENT - WATER)
Sodium Hypochlorite System Replacement Project - Cancellation and Budget Adjustment (ENVIRONMENTAL UTILITIES DEPARTMENT)
Water Meter Retrofit Project - Budget Adjustment (ENVIRONMENTAL UTILITIES DEPARTMENT - TECHNICAL SERVICES)
Operation and Maintenance of Woodcreek Intertie Improvements - Agreement (ENVIRONMENTAL UTILITIES DEPARTMENT - WATER)
Recycled Water Storage Improvements – New Capital Improvement Project Approval, Project Cancellation and Budget Adjustment (ENVIRONMENTAL UTILITIES DEPARTMENT - WASTEWATER)
Solid Waste Compliance – Professional Services Agreement Amendment (ENVIRONMENTAL UTILITIES DEPARTMENT - STRATEGIC AFFAIRS DIVISION )
Voting record (2)(Environment)
Oldest to newest — hover a bar for the item.